Why Plan Review Submissions Come Back, and a Pre-Submission Checklist
A returned submission rarely means the design is wrong. More often it means the reviewer could not confirm that it is right: a sheet is missing, two drawings disagree, a calculation is referenced but not attached, or a required signature is absent. Each comment adds a resubmission cycle, and each cycle adds time to a schedule that is already running.
This article lists the reasons submissions most commonly come back and ends with a pre-submission checklist you can adapt. It is deliberately jurisdiction-neutral. In the United States, plans go to the local building department; in England and Wales, to building control; in Canada and across the EU, to the building authority defined by provincial or national law. Each has its own forms, adopted code editions, local amendments and submission rules. Use this list as a starting point and confirm the local requirements with the authority that will review your project.
1. Incomplete package
The most common and most avoidable reason. The reviewer cannot start, or stops early, because something required is not there.
- Application form incomplete or unsigned, or the wrong form for the type of work.
- Sheets listed in the index but not included, or included but not listed.
- Disciplines missing: structural, mechanical, electrical, plumbing or fire protection drawings required for the scope but not submitted, or marked "by others" with no indication of when they will follow.
- Supporting documents absent: site plan, survey, soils or geotechnical report, specifications, product data for regulated items.
- Owner authorisation or agent letter missing where the applicant is not the owner.
2. Sheets that contradict each other
Every sheet may be correct alone while the set disagrees. Reviewers notice, because they cross-reference the same values the code depends on.
- Building height, storey count or floor area differs between the code summary, the plans and the elevations.
- Occupancy classification or construction type stated differently on two sheets.
- A wall shown as fire-rated on the plan but not in the wall type legend, or with a different rating.
- Door, window or room numbers that do not match the schedules.
- Structural grids or levels that differ from the architectural ones.
- References to details or sheets that do not exist.
For a systematic way to find these, see the 12-point construction document review checklist.
3. Egress details
Means of escape is one of the first things a reviewer checks, and the drawings must make it possible to verify.
- Occupant load not stated, or stated without the area and factor it was calculated from.
- Exit paths, travel distances and common path of travel not shown where required.
- Number and width of exits not reconciled with the occupant load.
- Door swing direction, hardware and stair dimensions missing or inconsistent with details.
- Exit signage and emergency lighting not shown where the scope requires it.
The numerical requirements differ by code and edition, so cite the code your jurisdiction has adopted and show the calculation on the drawings rather than just the result.
4. Accessibility details
Accessibility comments are frequent because the requirements are dimensional and the drawings often show intent rather than dimensions.
- Accessible route not identified from the site arrival point to the entrance and through the building.
- Ramp slopes, landings and handrails not dimensioned.
- Door clear widths and maneuvering clearances not shown.
- Accessible toilet rooms without enlarged plans showing fixture locations and clear floor space.
- Accessible parking, signage or wayfinding not addressed where required.
In the US, the 2010 ADA Standards for Accessible Design and the accessibility provisions of the locally adopted building code may both apply. Other countries use different standards. Confirm which apply to your project and which edition is in force.
5. Energy compliance documentation
Most jurisdictions require evidence that the design meets the adopted energy code or regulation. In the US this commonly means compliance forms under the adopted energy code; in England, calculations under Part L of the Building Regulations; elsewhere, the national method. Typical problems:
- Compliance report missing or prepared for an earlier design.
- Insulation values, glazing performance or equipment efficiencies in the report that do not match the drawings or specifications.
- Window areas in the report that differ from the elevations.
- Report not signed by the person responsible where a signature is required.
- Report prepared under a code edition or method not accepted by the authority.
The fix is reconciliation: every value in the energy report should be traceable to a drawing or specification, and the other way round.
6. Missing calculations, signatures or stamps
- Structural calculations referenced on the drawings but not submitted, or submitted for a different scheme.
- Mechanical, plumbing or electrical load calculations missing where required.
- Drawings not signed or sealed by the responsible licensed professional where the jurisdiction requires it, or sealed by someone not licensed in that jurisdiction.
- Deferred submittals (for example trusses, sprinklers or specialty systems) not listed as deferred, or listed without the information the authority needs.
- Revisions issued in response to earlier comments without revision clouds, a revision log or a written response to each comment.
Pre-submission checklist
Adapt this list to your project and to the authority's own checklist, which takes precedence where one exists.
- Obtain the authority's current submission requirements and checklist, and note the adopted code editions and local amendments.
- Confirm the application form is the correct one, complete and signed, with owner authorisation if needed.
- Reconcile the sheet index with the sheets actually in the set, for every discipline.
- Check that the code summary (occupancy, construction type, height, storeys, area, occupant load) is the same on every sheet that repeats it.
- Follow every "see sheet" and "see detail" reference to a real target.
- Confirm door, window, room and wall type tags match their schedules and legends.
- Show egress calculations and paths, not just results.
- Dimension the accessible route, ramps, doors and accessible rooms.
- Reconcile the energy compliance report with drawings and specifications.
- Attach all referenced calculations and reports, prepared for the current design.
- Check signatures and seals against the jurisdiction's rules.
- List deferred submittals clearly.
- For resubmissions, include a response to each comment and mark every revised area.
- Make sure file names, formats and sizes meet the authority's electronic submission rules.
When a submission does come back
Even a well-prepared package can receive comments. How you respond decides whether the second review is quick or becomes a third cycle.
- Read every comment before changing anything. Several comments often trace back to one root cause, such as a code summary that was not updated. Fixing the cause once is better than patching each symptom.
- Ask when a comment is unclear. A short question to the reviewer usually costs less than a resubmission that answers the wrong question.
- Fix the whole set, not one sheet. If a value changes, find every sheet, schedule, calculation and report that repeats it. A correction on one sheet that creates a new inconsistency on another is a common cause of further comments.
- Write a response for each comment. State what changed and where: sheet number, detail and revision. If you disagree with a comment, explain why and cite the provision you rely on.
- Re-check before resubmitting. Run the same pre-submission checks on the revised package, because late edits are where new errors appear.
Practical habits that reduce comment cycles
- Freeze before you check. Run the check on the set you will actually submit, not on a working version that keeps changing.
- Check the seams. Most comments come from the boundaries between disciplines and between drawings and supporting reports.
- Answer comments in writing. A response letter keyed to each comment shortens the reviewer's second pass.
- Keep the cost side in view. Changes made to satisfy plan review often affect the budget; see how to handle change orders and how to size and track contingency.
Where MEXUM fits
MEXUM checks a design package before submission: completeness against the sheet index, consistency between sheets and disciplines, and the references and requirements against the codes of the project region. The written conclusion arrives as a PDF within 24 hours, each finding with a quote and a page reference. It is a preparation step. It does not replace plan review by the authority or the responsibility of the licensed professional who signs the drawings.
Frequently asked questions
What is the most common reason a permit submission is returned?
An incomplete package is among the most common and most avoidable: missing sheets, missing disciplines, unsigned forms or referenced reports that were not attached. Many authorities stop reviewing until the package is complete.
Does this checklist apply to my jurisdiction?
It is a general starting point. Building departments in the US, building control in the UK and building authorities in Canada and the EU each have their own forms, adopted code editions and local amendments. Always confirm the local requirements and use the authority's own checklist where one exists.
Why do energy compliance reports cause comments?
Usually because the report does not match the drawings: different insulation values, glazing data, window areas or equipment efficiencies, or a report prepared for an earlier design. Every value should be traceable between the report and the drawings.
Can a pre-submission check guarantee approval?
No. It reduces avoidable comments by finding gaps and inconsistencies first, but approval is decided by the authority, and the design remains the responsibility of the licensed professionals who prepared and signed it.