← All articles

For lenders · October 3, 2026

Construction Loan Underwriting: What to Verify in the Borrower's Budget Before Closing

The credit memo is drafted. The borrower's package arrived as a single PDF: a budget summary on two pages, a schedule of values, a signed contract, and a drawing set that is labelled "for permit" rather than "for construction". The equity is in, the appraisal supports the as-complete value, and the closing date is fixed. Someone asks whether the budget has been checked, and the honest answer is that it has been read, not tested.

That gap is where most construction loan problems start. A budget that is internally consistent can still be wrong against the drawings, light on scope, or built on rates that no subcontractor will honour. The lender usually discovers this at draw four, when the loan is already out of balance and the remaining funds no longer finish the building. The checks below are meant to be done before closing, when the lender still has leverage.

1. Reconcile the budget to the drawings and scope

Start with what is being built, not what it costs. The budget should trace to a specific drawing set, identified by issue date and revision, and the lender file should record which set it is.

Check that each major scope item has a budget line, and each budget line has a scope item. Missing lines are more dangerous than inflated ones: fire protection, elevators, façade, site utilities, off-site works and testing are common omissions.

2. Test the schedule of values

The schedule of values is the contract price broken into the lines against which draws will be requested, so it is the document the loan will actually be administered from.

3. Separate hard costs from soft costs

Hard costs are the construction contract and directly related items. Soft costs include design and engineering fees, permits and impact fees, legal, insurance, financing costs, developer fee, marketing and lease-up costs. Each category fails in a different way.

Ask for the developer fee and any related-party charges to be shown as separate lines. Fees paid to affiliates of the borrower are not wrong in themselves, but they should be visible, and the timing of their payment should be agreed with the lender.

4. Assess contingency and allowances

There are two different safety margins and they should not be mixed. A contingency is a reserve for unknown cost; an allowance is a placeholder for a known item whose selection or price is not yet fixed.

There is no universal correct contingency percentage, and you should be sceptical of anyone who quotes one without reference to design stage, contract type and site. Set the amount by reasoning about specific risks, and document that reasoning.

5. Check quantities and unit rates

Two questions: are the quantities supported by the drawings, and are the prices supported by the market?

6. Understand the contract type: lump sum, cost-plus, GMP

The same budget carries different risk depending on who bears overruns.

Standard forms exist for each approach, among them the AIA A101 and A102 series in the United States, CCDC 2 in Canada and FIDIC forms widely used internationally. Check the current edition and any amendments for your jurisdiction, because amendments often change risk allocation more than the base form does.

7. Retainage, cost-to-complete and independent cost review

Retainage. Confirm the retainage percentage in the contract matches the loan agreement, when it is released, and what law applies to it where the project sits. Retainage rules vary by jurisdiction and by public or private project status; take advice locally. A contract that reduces or releases retainage early weakens the lender's position at the point where completion risk is still high.

Cost-to-complete. Before closing, establish a clear method for the loan to stay in balance: remaining hard cost, remaining soft cost and interest reserve must be compared with undisbursed loan funds and committed equity at every draw. Agree in advance what happens when the loan is out of balance, and whether the borrower must deposit funds before the next advance.

Third-party review. Lenders commonly engage an independent construction consultant or cost reviewer. Give that reviewer a precise assignment: which drawing set, which questions, which deliverable. A review that covers "the budget" in general terms tends to confirm what the borrower already said.

8. Permits and utility approvals as conditions precedent

A budget is only meaningful for a project that can legally be built. Make the following conditions to the first advance, or at least to advances beyond site work:

  1. Building permit issued for the drawing set that was priced, not an earlier version.
  2. Zoning and planning approvals final, with appeal periods expired where applicable.
  3. Utility capacity and connection agreements in place, with the connection costs and schedule reflected in the budget.
  4. Environmental and geotechnical reports reviewed, with their recommendations priced.
  5. Builder's risk and liability insurance bound, with the lender named as required.
  6. Payment and performance security from the contractor where the loan structure relies on it.

Utility approvals are frequently the item that delays a project by months without any change in the budget, and the interest reserve is what pays for that delay.

9. Red flags in the borrower package

Where an independent document review fits

MEXUM is a service that reviews design, cost and contract documents and returns a reasoned conclusion as a PDF within 48 hours. In a lending workflow it is useful at one specific point: before the credit committee or closing, when the borrower package exists and the lender wants a structured second reading of it. The review compares budget, drawings and contract for consistency, notes unsupported quantities and rates, and lists open questions for the borrower.

It does not replace the lender's own underwriting, the independent construction consultant, the site inspector or the lawyer. It does not certify progress, approve draws or give legal opinions. Its purpose is narrower: to make sure the right questions are on the table before the loan documents are signed.

This article is general information and not legal or financial advice.

Frequently asked questions

Why check the borrower's budget before closing instead of during construction?

Before closing, the lender still has leverage. A budget can be internally consistent yet wrong against the drawings, light on scope, or built on rates no subcontractor will honour. If this is discovered at a later draw, the loan may already be out of balance and the remaining funds may no longer finish the building.

What is the difference between contingency and allowances in a construction budget?

A contingency is a reserve for unknown cost, while an allowance is a placeholder for a known item whose selection or price is not yet fixed. They should not be mixed. Low allowances for finishes, fixtures, specialty equipment or site conditions are a common way to present a lower total, so each should be compared with a realistic price.

Is there a correct contingency percentage for a construction loan?

The article says there is no universal correct percentage, and advises scepticism toward anyone who quotes one without reference to design stage, contract type and site. The amount should be set by reasoning about specific risks, and that reasoning should be documented. A fully drawn new building on a clean site and a renovation of an occupied structure should not carry the same figure.

What red flags should a lender look for in a borrower's budget package?

Examples include a budget with fewer lines than the drawings have disciplines, round numbers on lines that should be calculated from quantities, very low contingency, an undated or unsigned contractor quote, early related-party or developer fees, different totals for the same item across documents, and drawings marked preliminary or a specification with missing sections.